The site is located in east County
Clare within the Sleive Aughty Mountains adjacent to the
Gort to Tulla Road. The proposal is to install eight x 3MW
turbines that will produce enough electricity to power 22,000 Irish
houses.
The site is on land owned by Coillte and is planted with conifers. It benefits from excellent access, wind resource and a Gate 2 grid connection.
The project is now owned by SWS Ltd. Pending receipt of full planning consent during 2010 then the wind farm will be financed and constructed by SWS in 2011.